Three-channel DC Resistance Tester Test Operation Method

Sep 22, 2025

Leave a message

When measuring the DC resistance of transformer windings, especially for those with a star (Y) connection and a neutral point lead-out, traditional single-channel instruments require separate measurements of A0, B0, and C0. After each measurement, a thorough discharge is necessary before proceeding to the next one, making the entire process very time-consuming. For large transformers, the winding inductance is significant, and the charging and discharging times are long, potentially making the testing process last for several hours.

The core advantages of the three-channel DC resistance tester:
Simultaneous measurement, extremely efficient: Charge all three-phase windings simultaneously and measure the resistance values of each phase at the same time. This reduces the traditional testing time of several hours to just a few minutes or even less.
Elimination of measurement errors: Due to simultaneous measurement, the temperature of the windings remains almost constant, avoiding errors caused by different temperature rises due to the time difference between successive measurements. This makes the calculation of the three-phase resistance imbalance rate more accurate.
Direct calculation of imbalance rate: The instrument automatically calculates and displays the three-phase resistance imbalance rate, eliminating the need for manual calculation.
Significant reduction in discharge time: Although discharging simultaneously for all three phases involves greater energy, the instrument is typically equipped with a powerful discharge circuit that can effectively control the discharge process.
Three-channel DC resistance tester
Application scenarios of the three-channel DC resistance tester
Factory test of power transformers: Inspect each transformer at the manufacturing plant.
Commissioning test of transformers: Acceptance testing before new equipment is installed and put into operation.
Preventive test (pre-test): Regular inspections (such as once every 1-3 years), to determine if there are any potential problems with the windings.
Fault diagnosis: When suspecting problems such as inter-turn short circuits, poor contact of leads, or faults in the tap changer, perform measurements for diagnosis.
Test steps of the three-channel DC resistance tester
Safety preparations: Power off, test for electricity, hang grounding wires, discharge! Ensure that all sides of the transformer are completely isolated and reliably grounded. Remove or disconnect all external connection lines before testing.
Test wiring:
Connect the instrument's current output line (I+) and voltage measurement line (V+) to the top of the A, B, and C phase bushings of the transformer. (For YN connected windings)
Connect the corresponding current return line (I-) and voltage measurement line (V-) to the neutral point (O) of the transformer.
Ensure all connections are secure and in good contact.
Parameter settings: Power on, select the appropriate test current (usually the instrument can automatically recommend it), and the type of winding (YN or D, for delta-connected windings, use different methods).
Start testing: Start the test. The instrument will charge all three-phase windings simultaneously and display the charging current and real-time resistance value changes.
Read the results: When the resistance value stabilizes (with a change rate less than a certain value), the instrument will automatically lock the data and display the resistance values of A, B, and C phases and their imbalance rates.
Discharge and line removal: After the test, do not remove the lines immediately! Wait for the instrument to automatically discharge until the screen shows "Discharge Complete" or the discharge indicator light goes out, then use a discharge rod to fully discharge the windings and finally remove all test lines.
Safety considerations for on-site testing
Safety first, thorough discharge: Transformer windings are large inductors, storing a huge amount of energy. The "Discharge Complete" displayed by the instrument only indicates the internal energy release. The windings themselves may still have residual voltage. It is necessary to use a dedicated discharge rod for multiple earth discharges to confirm that there is no charge before removing the lines. This is the most important point!
Correct wiring: Always use the four-wire method. The voltage lines (V+, V-) should be on the inner side of the current lines (I+, I-) and directly connected to the winding terminals to avoid including contact resistance.
Eliminate residual magnetic field influence: After multiple consecutive tests or changing the tap position, the residual magnetic field in the iron core will affect the charging speed. The "Demagnetization" function or changing the test polarity can reduce the influence.
Record the ambient temperature: Accurately record the upper oil temperature or winding temperature to facilitate accurate temperature conversion and comparison with the factory values.
Judgment of test results:
Main indicators: The imbalance rate of the three-phase resistance values. Standard requirements: For transformers with a capacity of 1600 kVA and above, the difference between the resistances of each phase winding should not exceed 2% of the average value of the three phases (for transformers without a neutral point lead-out, the difference between phases is not much greater than 1%).
Vertical comparison: The phase resistance or line resistance values measured in this test should not have significant differences compared with the factory values and previous test values (converted to the same temperature).